Who is this for ?
Anyone who reads dates in Pelico and needs to know what they mean, where they come from, and why they sometimes look wrong.
What you will learn :
The difference between the dates you gave Pelico and the dates Pelico calculates, how to read a delay, why late and blocked are not the same thing, and how Pelico counts days.
1. Two kinds of dates
Every date in Pelico is one of two things, and telling them apart saves a lot of time.
| Dates you gave Pelico | Dates Pelico calculated |
Where they come from | Your source systems | Pelico, from your plan |
Examples | Planned dates on orders, supplier delivery dates, customer commitments | Suggested start dates, production stop dates, delays |
If it looks wrong | Correct it in your source system | Ask what the calculation used |
💡Pelico never changes a planned date on its own. It calculates what your dates imply, and it suggests better ones. Moving an order is always a decision someone makes.
2. The dates Pelico calculates for you
Three calculated dates answer three different questions. They are easy to mix up because their names are similar, so it helps to remember the question each one answers.
Date | It belongs to | The question it answers |
Production stop date | An equipment | When does production of this equipment actually stop ? |
Next enablement date | A blocked order | If I cannot unblock this order, how far do I have to move it ? |
Blocking prod date | A part | Which part should I chase first, and by when ? |
The first is the deadline you are working against. The second is your fallback if you cannot meet it. The third tells you where to start.
⚠️ The next enablement date appears in the Work Order Book as the Suggested Start Date column. Same number, two names. If you compare this documentation with your screen, that is why.
One timeline carrying all three dates, each labelled with the question it answers. Already listed as a visual to add in Stock Projection, so produce it once and use it in both articles.
3. Reading a delay
A delay in Pelico is the gap between when material arrives and when it is needed. The sign is what matters, and it is easy to read backwards.
Delay | Meaning |
Positive | The material arrives after it is needed. This is a problem. |
Zero or negative | The material arrives on time or early. This is fine. |
So a delay of 5 means material lands five days too late. A delay of −3 means it lands three days early.
You can see delays in the Event Explorer, alongside the upstream and downstream links of an event, and in the upstream and downstream event columns of the Books where they are available.
4. Late is not the same as blocked
This is the most common confusion about dates in Pelico, and it changes what you should do about it.
| Late | Blocked |
Measures | Schedule | Material |
Means | The planned date has already passed | No supply solution exists for a component |
Comes from | Comparing a date to today | Coverage calculations |
The two are independent. An order can be late and fully covered. It can be blocked and not yet late. It can be both.
⚠️ A plant with many late orders and good coverage has a scheduling problem, not a material problem. If you read those two as the same thing, your team ends up chasing suppliers when the real issue is releasing work on time.
See Pelico’s Algorithms for how coverage itself is calculated.
5. How Pelico counts days
Calculated dates are counted in working days, in the time zone of the plant concerned, not in calendar days.
This is usually why a suggested date lands further out than you expected. Five working days across a weekend is seven calendar days.
⚠️ Pelico excludes weekends, but it does not know your factory calendar. Public holidays, plant shutdowns and shift patterns are not part of these calculations. A suggested date can land on a day your plant is closed.
Calendar strip showing a five working day span crossing a weekend. Already listed as a visual to add in Pelico’s Algorithms, so reuse the same one.
6. Why a calculated date can look impossible
A suggested date sometimes looks wrong to the people who would have to meet it. There are two reasons, and neither is a fault in your data.
It does not know your capacity
The next enablement date tells you when material and upstream work allow a start. It does not ask whether you have the capacity to start. There is no work centre capacity in that calculation.
So if your shop floor says the date is impossible, that is not a contradiction. Pelico was never asked that question.
It assumes the best case upstream
The calculation assumes every sub-assembly involved is produced in an optimised way. Your real plan for those sub-assemblies may be different.
This is why moving an order to its suggested date does not guarantee it becomes covered. If it stays blocked after the move, this is usually the reason.
7. Dates that have already passed
Pelico does not quietly reschedule an overdue order. It keeps it at its planned date and applies specific rules.
Situation | What Pelico does |
A past supplier delivery that never arrived | The stock is not added. Supply that should already have arrived is not assumed to arrive. |
A past production or transfer that was covered | Treated as if it happened. Components consumed, output added. |
A blocked production or transfer, past or future | Stays at its planned date. Components consumed, output not added. |
⚠️ This is why today's stock figure can differ from what is physically on your shelves. Overdue orders that nobody rescheduled are replayed at their old planned date.
8. When a delay is not about your plan
Before investigating a date, check Last data update. If your data was loaded this morning, a change made in your ERP this afternoon is not in Pelico yet.
This is worth ruling out first, because it looks exactly like a calculation problem. See the Data article.