MRO Usage Scenarios

B
Written by Baptiste Saussine

Who is this for ?

  • MRO managers

  • kitting managers

  • aftermarket planners

  • anyone working service orders day to day

What you will learn:

  • ten common situations in the MRO app, and the steps to work through each one.


Scenarios at a glance

You want to

Start here

See what repair work is left on an order

Service Order Book → Heatmap view

Allocate a rotable part to a constrained equipment

Service Order Book → Heatmap view

Keep your rotable pool healthy

Service Order Book

Check a subcontractor will deliver on time

Service Order Book → PO 360 view

Find an alternative plan with your production counterpart

Equipment 360 view

Push covered service orders to repair, worst OTD risk first

Service Order Book

Unblock a service order after kitting

Service Order Book → Gate 3

Escalate missing parts at the kitting gate

Service Order Book → Gate 2

Prioritize Asset On Ground orders

Service Order Book

Rebalance weekly capacity across work centers

Capacity view


1. Review the repair work left on an order

You want to see which sub-repairs remain, and make sure the shop is working on what the top-level equipment actually needs.

  1. Open the Service Order Book and select the Heatmap view.

  2. Then, depending on how complex the order is:

For simple orders

  • Add the Workscope column, hidden by default, and filter on Repair service orders.

  • Or open the service order's 360 view and look at the Repair Orders section.

For complex orders

  • Use the Tree view and look at the leaves of the tree: the service order parts appear there, and repair service orders are easy to pick out.

  • Or open the service order's 360 view, where the repair service order appears under Upstream Events.


💡The reason this matters: a shop working hard on a sub-repair that isn't holding up the top-level equipment is a shop missing its customer date for no good reason.


2. Allocate a rotable part to an equipment under constraint

You want to find a rotable that fits, and get the right people to agree on using it.

  1. In the Service Order Book, use the Heatmap view to list service orders and spot the blocking parts.

  2. Look for the 💡 lightbulb on red cells and open its tooltip. Rotable opportunities appear there, marked with a recycle icon and a quantity.

  3. Open the service order's 360 view and leave a comment saying which rotable should be used.


💡 Rotables can appear two ways. Inside the lightbulb tooltip alongside the other Stock Improvement Opportunities, and also as a standalone Rotable tag on its own. Both point to the same thing.


3. Keep your rotable pool healthy

You oversee repairs on internal equipment so you can keep offering standard exchanges.

  1. Open the Service Order Book and look for equipment carrying the rotable icon.

  2. Select an equipment and check its buffer stock of rotables.

  3. Once you have identified the rotable to use, create a ticket asking the storekeeper to allocate that part to the target service order.


4. Check a subcontractor will deliver on time

  1. Open the Service Order Book.

  2. Set the Subcontracted filter to Yes.

  3. Select the subcontracted icon next to the service order number to open the purchase order 360 view.

  4. Check the delivery date is earlier than the date your customer asked for.


5. Find an alternative plan with your production counterpart

You want a plan that works for both manufacturing and aftermarket, rather than one at the expense of the other.

  1. Open the Equipment 360 view for a full picture of the equipment and everything attached to it.

  2. Use the Plant dropdown, top right, to switch between plants and see the equipment as it stands at each one.

  3. Check the Stock Transfer Orders to see what is already moving between your sites.


6. Push covered service orders to repair, worst OTD risk first

  1. Open the Service Order Book and set Material Coverage to Covered, to find orders with everything they need.

  2. Set the OTD filter to At Risk, to find orders in danger of missing their date.

  3. Work the resulting list: these orders can move now, and they are the ones that hurt if they don't.

  4. Prioritize them for repair and reassembly, and decide what needs reallocating, rescheduling or expediting.


💡These two filters together are the highest-value combination in the app. Covered means nothing is stopping you. At risk means it matters. Everything on that list is work you can start today that protects a customer date.


7. Unblock a service order after kitting

Parts can go missing after kitting: something broke, something was missed during analysis, an engineering decision came late.

  1. Open the Service Order Book and set the current gate filter to Gate 3, after logistics.

  2. Set Material Coverage to Blocked.

  3. Use the Heatmap view to see which missing parts are attached to each service order.

  4. Work with the reassembly operators to clear the blockers.

  5. Follow the orders afterwards to confirm they are moving again.


8. Escalate missing parts at the kitting gate

  1. Open the Service Order Book and select the Heatmap view.

  2. Apply the Material Coverage filter to find orders with missing parts.

  3. Set the gate filter to Gate 2, kitting.

  4. Identify the missing parts and escalate them to your supply chain team.

  5. Follow the escalations until the parts are secured.


9. Prioritize Asset On Ground orders

  1. Open the Service Order Book.

  2. Apply the Escalation Level filter to find Asset On Ground orders. The tier that means AOG is the one agreed with your customer.

  3. Use the Heatmap view to see and simulate the required coverage date for these orders.

  4. Prioritize them.

  5. Check what prioritizing them does to your other orders, and adjust where resources go.

💡 Step 5 is the one people skip. An AOG order pulled forward takes parts and capacity from somewhere. Better to know where from than to discover it next week.


10. Rebalance weekly capacity across work centers

  1. Open the Capacity view.

  2. Use the work center filter to select the work centers that matter for your current priorities.

  3. Look for capacity shortages that would stop you meeting them.

  4. Edit the capacity allocations to move resource where it is needed.


Assumptions & limitations

  • Every scenario assumes your plant scope and filters are already set for your perimeter.

  • Gate numbering (Gate 2 kitting, Gate 3 after logistics) comes from the source article. Gate configuration is usually specific to each organization, so your own gate numbers and names may differ.

  • Escalation tiers, including which tier means Asset On Ground, are agreed between you and your customer. There is no universal rule.


Glossary

Term

Definition

Asset On Ground (AOG)

An asset out of service and waiting on a repair, usually the highest priority a service order can carry.

Capacity view

The MRO view showing workload against available capacity, by work center and by week.

Gate

A stage in the repair process. Orders move from gate to gate as work progresses.

Heatmap view

The Service Order Book view showing coverage as coloured cells, so shortages stand out.

Rotable

A part that is repaired and returned to service rather than scrapped, and can be swapped between equipments.

Service Order (SO)

An order to repair, maintain or overhaul an item.

Standard exchange

Giving a customer a serviceable unit from your pool instead of waiting for their own unit to be repaired.

Tree view

The view showing service orders as a hierarchy, useful on complex orders with many sub-repairs.

Workscope

The kind of work a service order covers. A column in the Service Order Book, hidden by default.