Introduction to Planning

B
Written by Baptiste Saussine

Who is this for ?

  • Planners

  • production managers

  • central supply chain teams who work part by part rather than order by order

What you will learn:

  • how the Planning app organises your data

  • what each of its features shows

  • what you can do in bulk, and how Planning differs from Supply Planning


1. What the Planning app is for

Most Pelico apps are organised around orders. Planning is organised around parts.

You pick a part, and you see everything that happens to it over time: what is coming in, what is going out, and what your stock will look like at the end of each day, week or month. It is the view you use when your question is about a part rather than about an order.

Use it to manage production schedules, watch stock levels, and see where your resources do not match your needs.

💡 The quickest way to know whether you want this app: if your question starts with a part number, come here. If it starts with an order number, use Production Control, MRO, Supply or Customer Support instead.


2. How the view is organised

Planning groups data by equipment or part, and adds up production and supply events into time buckets. You choose the bucket size: days, weeks or months.

So one row is one part, and the columns are periods of time.


3. What you can see

3.1 Projected stock

Your stock level for each time period, daily, weekly or monthly. This is where you spot a shortage before it happens and act while you still can.

3.2 Needs and resources

Two sides of the same question.

Line

What it shows

Needs

Total demand for the part

Resources

Total supply available for the part

You can open either one to see the detail by object type: customer orders (CO), purchase orders (PO), work orders (WO), and others.

💡 Reading needs and resources side by side tells you why your projected stock moves. The projected stock line tells you that you have a problem in week 9. These two lines tell you whether it is because demand went up or supply went down, which decides who you call.

3.3 Detailed breakdowns

You can break needs and resources down further, by the party involved.

Break down by

For which object

Client

Customer orders (CO)

Supplier

Purchase orders (PO)

Plant

Stock transfer orders (STO)

Status

Work orders (WO)

3.4 Split view: equipments and consumed parts

This view is built for production managers and central supply chain teams. You switch between Equipments and Consumed Parts, so you can see a missing component and what it does to the production schedule above it.

To switch this on, apply at least one equipment filter. Without a filter the split view is not available.

💡 This is the feature that connects the part-level view back to your product. You start from a shortage on a component and end up looking at the equipment it will stop.


4. Customising your view

Open View Settings to change what the view shows. Filters and columns work the same way as in every other Pelico app: filters near the app name at the top, the columns panel on the right.

Once you have a set-up you like, save it as a routine so you do not rebuild it every morning. See First steps on the Pelico platform.


5. Bulk actions

Bulk actions let you act on several parts at once instead of repeating the same change.

What you are acting on depends on your mode

Mode

You act on

By part in one plant

Plant parts

By part across plants

Parts

How to use them

  1. Tick the checkboxes on the parts you want.

  2. A blue box appears at the bottom of the page with the available actions.

The three actions available today

Action

What it does

Add as filter

Turns your selection into a filter

Reset simulation input

Clears the simulated values on the selected parts

Simulate cycle time

Simulates a cycle time change on the selected parts

⚠️ You cannot mix sections. If you select a part in the Equipments section, the checkboxes in the Consumed Parts section become unavailable, and the other way round. Finish one section before you start the other.


6. Downloading your data

You can export planning data for offline analysis. Whether this is available depends on your configuration.

⚠️ The export contains the event data for each part, not the whole Planning view as you see it on screen. If you were expecting the grid, the file will look different from what you left.


7. Planning or Supply Planning?

These two views look similar and cover different things.

Planning

Supply Planning

Which parts

All parts with stock or event information

Buy-related parts with at least one supply event

Views

Equipments and Consumed Parts

Supply events

Use it when

You want the broad picture for a part

You are working on the buy side

💡 In short: Planning is wider, Supply Planning is more focused. If a part you expect is missing from Supply Planning, check whether it is a make part with no supply event. It will be in Planning instead.


8. Glossary

Term

Definition

Bulk action

An action applied to several parts at once.

CO

Customer Order. Firm customer demand.

Consumed Parts

The components that go into an equipment. One half of the split view.

Cycle time

How long it takes to produce a part. Can be simulated in bulk.

Equipments

The finished or assembled items you produce. The other half of the split view.

Needs

Total demand for a part.

Part

An item tracked in Pelico, across all plants.

Plant part

An item tracked at one specific plant.

PO

Purchase Order.

Projected stock

Your expected stock level at a future point in time.

Resources

Total supply available for a part.

STO

Stock Transfer Order. A movement between two of your own plants.

Time unit

The size of each column: day, week or month.

WO

Work Order.


Did this answer your question?